FS#4310 — FS#8244 — High tension switch

Attached to Project— Datacenters
Maintenance
All of the datacenters
CLOSED
100%
We will perform a series of electric switches to supply the new rooms in Roubaix 2 and 5.

We work on it all day today.
Date:  Friday, 15 March 2013, 00:44AM
Reason for closing:  Done
Comment by OVH - Friday, 15 March 2013, 00:44AM

Works have finished at around 06:00pm, all went as expected.
New rooms could be connected and the installations' resilience is improved.